What to check in a ventilation package before you sign the M&E order

Home  /  Insights

Five minutes with the drawings now saves weeks of programme pain later.

Ventilation is one of the quieter packages in an M&E contract, right up until it is not. Most of the grief we see on site traces back to a handful of gaps that were visible in the tender documents all along. Here is what we look for before we price a package, and what we would suggest any project manager checks before signing one off.

First, make-up air. Extract is only half of a ventilation system: every cubic metre you pull out of a kitchen, workshop or plant space has to come from somewhere. If the package lists extract fans but nothing about how replacement air enters the building, the system will underperform the day it is switched on - doors whistle, canopies fail to capture, and the extract rates on the commissioning sheet become fiction. Ask where the make-up air comes from.

Second, coordination allowances. Ductwork is the largest service in the ceiling void and it always meets steel, sprinklers and cable containment somewhere. Check whether the package includes coordination drawings, and who owns the clash when the void is tighter than the drawings suggested. A package price that assumes a clear run is a change order waiting to happen.

Third, commissioning and documentation. Balancing a system takes real time at the end of the programme, exactly when everyone wants the site cleared. If commissioning, witnessing and O&M documentation are not explicitly in the package, they will be squeezed - and an unbalanced ventilation system is the single most common reason a completed building feels stuffy in some rooms and draughty in others.

Fourth, the exclusions list. A short exclusions list is not a generous package; it is usually an unexamined one. We would rather write down exactly what is not included - builders work, electrical connections, access equipment, out-of-hours working - than surprise anyone in month three.

None of this is complicated, but it decides whether the ventilation package lands quietly on programme or becomes the last trade on site. If you have a tender in front of you and want a second pair of eyes, send the drawings over - reviewing them is free.